Alameda County Water District

Clients > Alameda County Water District

Client Details

Construction Value$600k
Services ProvidedConstruction Inspection Services
Service Date2016
Client ReferenceDorota Budzynska, Alameda County Water District
Project TypesUtilities

Iron Horse Lane Water Main Replacement Project – Fremont, California 

Description:
The $600,000 project included installation of over 1,000-feet of new 6-inch diameter PVC and steel pipe water main, along with a number of service laterals, to meet current ACWD standards.

The three-block water main replacement project was in Niles Community of Fremont.

The work included involves:

  • Installation of new 6-inch water main pipe and service laterals
  • Potholing of existing utilities
  • Trench backfill & paving restoration
  • Traffic control – both for vehicles and pedestrians
  • Water Pollution Control
  • Public relations and outreach

The project area is along an alleyway adjacent to a mixture of business and residential buildings. Advance notice for closure of the roadway will be necessary to minimize inconvenience to businesses and residents.

Park Engineering provided Construction Inspection Services to monitor & document the contractor’s daily activities for contract compliance. Inspection staff reported directly to the District’s Project Manager and worked closely to supply all the necessary documentation to record and pay for the work performed.